Every plant has one step that limits how much it can ship. In a high-mix plant it hides well: routings vary, the mix changes weekly, and every department looks busy.
Why it’s hard to see
Utilisation reports make every machine look important, and the busiest-looking step is not always the limit. In high-mix plants the load moves with the mix, so last month’s problem step may not be this month’s. Start from evidence, not reputation.
Step 1: look for where work waits
The bottleneck has a queue in front of it. Walk the floor at shift start and note where work waits and how old it is. A queue always there, at the same step, is the strongest signal you will get.
- Where do jobs sit longest between operations?
- Which step do supervisors expedite around every day?
- Where does overtime keep landing?
Step 2: check it against your data
Pull three exports: open orders, routings with standard hours, and work in process by operation. For each work center, compare the hours due in the next few weeks with the hours it can actually run.
- Load against capacity: the most work due against real available hours marks your first candidate.
- Age of work in process: the oldest work tends to sit in front of the constraint.
- Routings against reality: where the floor’s path differs, trust the floor and fix the data.
Step 3: confirm it
If this step lost an hour, would the whole plant ship an hour less? If yes, it is the constraint. If the hour could be made up elsewhere, keep looking.
At a high-mix metal fabricator, finishing was the bottleneck, but the bigger problem was what it spent its time on. Coating adhesion failures traced to inconsistent pre-treatment, dimensional rejects to fixturing that varied by operator, and jobs sat on hold as travelers moved without complete inspection records. Every reworked part went through the bottleneck twice. Fixing the causes at the source gave that capacity back, without buying a machine.
At a powder-coating plant, color changeovers needing a full booth clean-out, not coating, took the most line time. Sequencing by color family and standardising racking so each pass carried more parts recovered real capacity on the existing line, without a second shift.
Step 4: decide what to do with it
Follow the Theory of Constraints: get the most out of the bottleneck, make every other step follow its pace, and only then add capacity. A schedule built around the bottleneck does that daily.
Next: how to schedule a bottleneck, drum-buffer-rope, explained or why the ERP schedule gets ignored.
New to a term? See the glossary.