The one-week Diagnostic ends in a written read-out. This one is for a made-up plant.

Sample plant

Diagnostic read-out

120 people · make-to-order · fabricated assemblies · one product family

The answer

Pace the line at Weld.

Go: start the Sprint.

On the floor
Week of
Read-out
Week of
Sample plant

1The map

One product family, from the floor and your own reports.

  1. 2 daysCut
  2. 1 dayForm
  3. 6 daysWeldPacemaker
  4. 1 dayPaint
  5. 3 daysAssemble
  6. 1 dayShip

Lead time: 15 working daysTouch time: 9 hours

  1. Work waits 14 of 15 days. Six of them are in front of Weld.
  2. Each step runs its own priority list, so Paint and Assemble get work in the wrong order.
  3. Orders are released when entered, not when parts are ready. Three days of work sit at Assemble, short of parts.
Sample plant

2Where to pace the line, and why

At Weld.

It sets the pace for this mix
Weld carries the heaviest load. What Weld finishes, the plant ships.
Setups
Fixture changes are long. Running by fixture family wins back time here first.
Shared resources
Certified welders also cover repair work. The schedule has to show it.
What the schedule must protect
The promise date. A schedule at Weld sets it for every step after.
  1. Release
  2. Cut
  3. Form
  4. 2 daysWeldPacemaker
  5. Paint
  6. Assemble
  7. 1 dayShip
Buffers
One in front of Weld: two days of ready work. One at shipping: one day. None elsewhere.
Release rule
Release work at Weld’s pace, only when parts are ready.
Day one
Cut and Form start only what the release list shows. Supervisors check the buffer each morning. Nothing in your ERP changes.
Sample plant

3Go or no-go, and the Sprint

Go.

If your reports arrive in the first days, and the master scheduler and supervisors have agreed time each day.

Six weeks

  1. Weeks 1–2Scheduling board set up from your reports.
  2. Weeks 3–4Release rule live. Daily buffer meeting starts.
  3. Weeks 5–6Your team runs it. We coach.

Who does what

Plant manager
Sponsors it and clears the way.
Master scheduler
Owns the daily release.
Supervisors
Run the daily buffer meeting.

Data gaps, and how we close them

Weld routings carry no setup times.
Timed on the floor in week 1.
Part shortages are not recorded.
Logged at release from week 3.

What an hour at Weld is worth

Units per hour ×Margin per unit =

Your figures, your arithmetic.

Start with one plant.

Start with a one-week Diagnostic at one plant. Where to pace the line and a go or no-go, or you don’t pay.