A plant’s capacity is set by one step. Knowing it tells you what the plant can really make, what the growth plan will cost, and whether the case depends on equipment you haven’t priced.
Why the usual numbers mislead
Nameplate capacity and average utilisation describe machines, not flow. A plant can show spare capacity on paper while one step (often finishing, heat treatment, test or a shared resource) limits everything it ships.
Five questions for the site visit
- Where does work wait, and how old is it?
- Which step do supervisors expedite around every day?
- Is work released at the bottleneck’s pace, or whenever material arrives?
- How much of the bottleneck’s time goes to rework, changeovers or waiting for kits?
- Does the system’s schedule match what the floor runs?
Data to request
- Open orders with due dates, and on-time delivery history
- Routings with standard hours, by work center
- Work in process by operation, with age
- Shift patterns and overtime by department
Full list: the due diligence checklist.
What it means for the value-creation plan
| Lever | What to quantify |
|---|---|
| Output | How much more the plant ships by protecting and pacing the bottleneck, before capital spend. |
| Capital | Equipment that can wait because the constraint’s lost time is recovered first. |
| Cash | Work in process that comes down when release is tied to the bottleneck. |
| Delivery | Lead times and on-time performance the plant can commit to. |
At a coating plant, color changeovers, not coating, took the most line time. Sequencing by color family recovered capacity on the existing line: the kind of finding that changes a capacity-expansion line item.
Next: the plant capacity check, our work with private equity operating teams or how to find the bottleneck in a high-mix plant.
New to a term? See the glossary.