Case studiesCase study · Beverage canning · Make to order

The canning filler, from about 24% effective to 42% in six months

A contract canning plant filling to order for many brand owners. Every hour the filler lost was lost for the whole plant. We set the pace at the canning line.

Filler effectivenessBefore: about 24%after: about 42%
After: kit ready before each changeover, longer runs.

The numbers

Filler effectiveness (share of planned time at full speed, good cans)Before: About 24%. After: About 42%.
Barrels packaged a day on the canning lineBefore: 364. After: 532.

Barrels a day: the November to February average before; the first two weeks of August after.

532barrels a day in early August, against a 364 average from November to February
About 42%filler effectiveness in August, from about 24% in February
Every machineon the line has a written changeover kit: materials and settings
1 ownerchecks the kit for each changeover before the line stops

Where it started

The canning line was built when the plant ran far fewer products for far fewer customers. Changeovers were frequent, and whether every material was there was checked on the day of the run, often during the changeover itself. Runs started late and needed adjusting while running, and the plant was expanding at the same time.

What we did

  1. Set the pace at the canning line: every hour lost there is lost for the whole plant.

  2. One team from engineering, maintenance, quality and every shift made the line reliable, machine by machine: written procedures, operator training, preventive maintenance.

  3. Full kit before every changeover: a list of every material and setting for each machine, and one owner who checks tanks and materials are ready before the line stops.

  4. Started building the schedule around the canning line: product families, a lead time for each, and work released from what ships.

Why it held. Each fix went into a written procedure, the training and the maintenance plan, and one person owns the kit for every changeover.

Start with one value stream.