Case study · Hand tools · High mix

More output from the same robots, with 40 people short

A two-plant hand-tool manufacturer with more than 75 product variants found its real bottleneck, scheduled the whole plant around it, and raised output while running short-staffed.

Under 2%retry rate at the bottleneck, down from 30–60%
30,000–35,000units a day through the bottleneck, up from 6,000–25,000, on four of five robots
+25%forge output, consistently over 150,000 pairs a week

Source: the implementation case study. Results measured by the client’s own team.

The plant

Two plants, more than 350 people and over 75 variants. Every finished tool is two matched halves that have to meet at final assembly, so a shortage of either half stops the whole order. Heat treatment runs on a robotic laser cell; forging runs on hammers with long changeovers.

The problem

  • Output at heat treatment swung widely from day to day, and up to 60% of parts had to be run again.
  • Work in process piled up everywhere, so the floor couldn’t see which matched pairs were really short.
  • Each department was measured on its own output, which kept every machine busy on the wrong work.
  • The plant was more than 40 people short through the year.

What we did

  1. Found the bottleneck by loading, not by opinion. The numbers pointed to the heat-treat laser cell for the main product stream.
  2. Changed the measures first. Departmental targets were replaced with one shipping-based productivity index, so every area pulled in the same direction.
  3. Choked the release. Excess work in process was frozen and physically moved to a holding area. Raw material was released only for items that would run short.
  4. Protected assembly with a buffer. Completed matched pairs were held at one stocking point in front of final assembly.
  5. One priority list, every day. A five-colour priority, recalculated daily from a matched-pair shortage rule, owned by one named person.
  6. Fixed the bottleneck’s losses. Failure-mode reviews and preventive measures cut the risk on the cell’s top failure modes (risk scores from 288 to 12 and from 140 to 30).

The results

  • Retry rate at the bottleneck: from 30–60% to under 2%.
  • Daily output through the bottleneck: from 6,000–25,000 to 30,000–35,000 units, on four of the five robots.
  • Forge output: consistently over 150,000 pairs a week, up 25%.
  • All of it achieved while the plant was more than 40 people short.
Why it held. This plant changed how it measured performance before it changed the schedule, and it kept the release choke in place. Those two decisions are what kept the gains after the project ended.

Another case study: The best shipping month in company history, three months in. See all case studies.

Is one step holding your plant back?

Take the free scorecard: ten questions, with an instant result.

Take the scorecard

See it on a plant like yours.

Tell us about your plant. We’ll tell you where we think the bottleneck is, and whether we can help.

Talk to us