The plant
Two plants, more than 350 people and over 75 variants. Every finished tool is two matched halves that have to meet at final assembly, so a shortage of either half stops the whole order. Heat treatment runs on a robotic laser cell; forging runs on hammers with long changeovers.
The problem
- Output at heat treatment swung widely from day to day, and up to 60% of parts had to be run again.
- Work in process piled up everywhere, so the floor couldn’t see which matched pairs were really short.
- Each department was measured on its own output, which kept every machine busy on the wrong work.
- The plant was more than 40 people short through the year.
What we did
- Found the bottleneck by loading, not by opinion. The numbers pointed to the heat-treat laser cell for the main product stream.
- Changed the measures first. Departmental targets were replaced with one shipping-based productivity index, so every area pulled in the same direction.
- Choked the release. Excess work in process was frozen and physically moved to a holding area. Raw material was released only for items that would run short.
- Protected assembly with a buffer. Completed matched pairs were held at one stocking point in front of final assembly.
- One priority list, every day. A five-colour priority, recalculated daily from a matched-pair shortage rule, owned by one named person.
- Fixed the bottleneck’s losses. Failure-mode reviews and preventive measures cut the risk on the cell’s top failure modes (risk scores from 288 to 12 and from 140 to 30).
The results
- Retry rate at the bottleneck: from 30–60% to under 2%.
- Daily output through the bottleneck: from 6,000–25,000 to 30,000–35,000 units, on four of the five robots.
- Forge output: consistently over 150,000 pairs a week, up 25%.
- All of it achieved while the plant was more than 40 people short.
Another case study: The best shipping month in company history, three months in. See all case studies.